Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-1-13/02/2023

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Burton Green
Contractor
BBV JV
Type of works
Road closure
Estimated Start Date
03/04/2023
Estimated End Date
01/09/2023

What we are doing

*Updated notice

3 April 2023 to 14 April 2023 dates have now changed to 3 April 2023 to 15 April 2023 at 1:30pm*

Ahead of temporarily realigning Cromwell Lane we have to divert multiple utilities and reconnect them during the diversion. We need to do this as their current location clashes with the realigned road. To carry out this work we will need to excavate a section of Cromwell Lane and relocate the utilities before then resurfacing the section. To be able to do this work safely we have to close Cromwell Lane between Red Lane and Hodgetts Lane.

Cromwell Lane will be closed between, Red Lane and Hodgetts Lane. These works will be carried out during the school half term break to minimize the disruption to the community. These works will be carried out on the following dates:

3 April 2023 to 14 April 2023

30 May 2023 to 2 June 2023

26 July 2023 to 1 September 2023

The closures will be in place 24 hours a day. A fully signposted diversion will be in place throughout the closures and access to all properties will be maintained. Cromwell Lane will remain open for pedestrians and cyclists.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]