Notice of road closure, Cromwell Lane-Burton Green

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-46-14/09/2023

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Burton Green
Contractor
BBV JV
Type of works
Road closure
Estimated Start Date
30/10/2023
Estimated End Date
16/12/2023

What we are doing

As part of our final realignment works on Cromwell Lane, we are required to carry out further programme of utility works on Cromwell Lane. To safely carry out the work we will need to close Cromwell Lane to create a safe working environment.

These works will be carried out in 2 phases.

Phase one works will start from 30 October to 25 November 2023.
Phase two works will start 04 December 2023 to 16 December 2023.
Please note that a closure will be in place 24 hours a day while these works are carried out. A fully signposted diversion will be in place throughout the closure with access to all properties maintained throughout. Cromwell Lane will remain open for pedestrians and cyclists.